Ralph Lauren
Client: Ralph Lauren
Contract name: New Cathedral St, Manchester
As part of a new design concept Manchester was one of a three store expansion. The unit is located within New Cathedral St, the high-end fashion arm of the Arndale Shopping Centre.
RTS were successful within a competitive tender process and installed as Main Contractor for this project. Sub-contractors were interviewed and vetted through our internal procedures and brought into the project to undertake packages such as :
> Structural
> Electrical
> HVAC inc plumbing
> Partitions and ceilings
> Flooring (timber and vinyl)
> Shutter
> Decoration
Taking the unit from a shell, RTS managed all aspects of the project including liaison with Centre Mgmt / security, online booking in system and client direct suppliers – CCTV, tagging, signage, IT, music, display / POS equipment.
Health & Safety was monitored through the submission of RAMS, inductions, regular daily / weekly meetings and periodic audits from our H&S advisors.
This project showcased Ralph Laurenís new high st concept and was successfully brought in on budget and timescale.
Completion date: September 2018